CAP1592: Interim report on the progress of airport-airline engagement on the new runway capacity at Heathrow Airport: September 2017

Please find below details of the CAA Publication you have selected. Dependent on availability, you are able to download the file, or purchase a printed copy.

 

EU exit

Please note that, in the event of the UK leaving the EU without a negotiated agreement, some CAA website content and application forms may continue to carry the EASA logo or reference the EU or EASA rather than the UK CAA in the short term. These will be updated in due course following the UK’s departure from the EU. In the meantime, the guidance provided and the application forms accessed via the CAA website portal will continue to be valid.

Reference:CAP1592
Title:Interim report on the progress of airport-airline engagement on the new runway capacity at Heathrow Airport: September 2017
Description:This document is our latest update to the Secretary of State (SoS) for Transport on how well Heathrow Airport Limited (HAL) has engaged with and responded to the airline community on the appropriate scope, design and costing of new runway capacity at Heathrow Airport.

The Terms of Reference (ToR) for this work require us to provide reports on a regular basis. We produced our first report in February 2017. This update describes the progress that HAL and the airlines have made since we provided our last report in May 2017.

Status:Current
Review Comment:None
Version:1
Date:September 2017
View File:Open document in new windowDownload PDF595kb
Purchase Copy:Printed copy not available for purchase